The Town of Longboat Key’s Greer Island Spit Management Project is underway. As a result, portions of the beach will be closed to the public during the construction period. The tentative schedule follows:
-
July 17 – July 28 – Mobilization of Upland Equipment and Dredge
-
July 24 – July 31 – Upland Clearing & Excavation
-
July 31 – August 14 – Hydraulic Dredging of Greer Island Spit
-
August 5 – August 8 – Hydraulic Dredging of Canal 1A
-
August 21 – August 23 – Beach Tilling
-
August 23 – September 4 – Demobilization
Please note this is a tentative schedule, subject to change. For more information, please contact the Public Works Department at 941-316-1988.
|